There are many stages of construction involved in building a new home. We have outlined the three major phases of construction to help you better understand the process and to help make it easy to know how and when to make selections for your new home. Please make your choices by date requested to help prevent delays in construction.

1. Home Plan and Property Lot are Selected
2. Contract is signed by a new Homeowners (Buyers) and Oakwood Custom Homes Group LTD
3. Financing is secured by new Homeowners
4. Finance Closing-Homeowners, Title and/or Mortgage Company, & Oakwood Custom Homes

The construction phase does not start until all steps in the Preliminary Phases are completed.

IMPORTANT- You will need to make arrangements for your utilities (electricity, water, sewer, and gas). We will make arrangements for your temporary power for construction. You will also need to get a 100-year flood plan certificate, and provide access to the property (culverts if needed, and a cleared path or road if in a rural area).

Exterior  Phase

1. Temp. Pole set, Forms are set and dirt is brought in to forms, Owner Selections for Exterior Phase
2. Plumbing Rough-In, Beams are dug, Termite Treatment, Steel in place, Pour Slab
3. Framing Structure, Owner Selections for Interior Phase
4. Framing Finished, Exterior Painted, Roof Installed, Construction Clean-Up
5. HVAC Rough-In, Plumbing Top-Out, Electrician Rough In
6. Inspections + - (Building, Electrical, HVAC, Plumbing); Insulation Installed (walls)
7. Insulation Inspection, Brick Installed, Sheetrock Installed, Tape and Float

Interior Phase

1. Texturing, Cabinets installed, Trim Carpenters Begin, Owner Selections for Finish Phase
2. Trim Carpenters Finish, Painter begins
3. Painting, Driveways and Porches Poured
4. Countertops Installed, Vanity Tops Installed, Marble Tubs Installed (If necessary)

Finish Phase

1. Tile installed, Electrician Trim-Out (Appliances and Lightning Fixtures Installed)
2. Plumbing Trim-Out, HVAC Trim Out
3. Fence, Sprinkler System Installed (if necessary), Carpet Installed
4. Inspections** (Building Final, HVAC Final, Plumbing Final, Electrical Final) if necessary
5. Grass installed, Final Clean-up, Customer Moves-In